Example draft question
Which entrance must remain available during phase 2, and at what times? May we propose temporary access for review in our bid?
Phasing plan · phase 2 work zone
Tender documents · access to the building
The phasing looks settled until you notice the building entrance sits inside your work zone. That affects both your bid and your programme. Baudex helps you compare the phasing plan with the access requirements. Your team decides what needs to be agreed before pricing and carrying out the work.
Worked example · Public realm works
The building stays in use. The phasing plan puts the work at the entrance while the tender specifies access. The team needs a practical agreement before submitting its bid.
Phasing plan and tender requirements
Access to an occupied building
Agreement needed
Where do the work zone and access overlap?
Building in use
Entrance
Work zone · phase 2
Schematic view of the worked example.
Put the work zone and entrance on the same plan. Check which phase 2 activity affects access so you can agree a suitable time window.
Share the phase and drawing reference
Keep the drawing extract with its sheet number and revision. Reference the same phase in the programme when you record the question.
Tender requirement · Access to the building
Who needs to enter?
Confirm
Which deliveries need access?
Confirm
Which entrance and times are required?
Open
The tender requires access. Confirm who needs it and when.
Visitors, staff and deliveries may need access at different times. Confirm who needs to get in and when before fixing your method and price.
Confirm the access requirements
Submit any temporary alternative to the client for review. Keep the issue open in the programme until a decision is made.
Draft question for the tender clarification round
Which entrance must remain available during phase 2, and at what times? May we propose temporary access for review in our bid?
Include the sheet, revision and phase when you submit the question.
Name the overlapping phase and the access requirement. Ask for a decision your team can use to update the work zone, programme and any temporary measures.
Carry the answer into the work
Update the work zone, timings and communication with building users. Check which measures affect the estimate.
Before bidding, record the work zone affected, who will follow up and which activity depends on the answer. Add the confirmed decision to the same row so the site team can trace it when a revision arrives.
Read about AI in tenderingWork zone
Phase 2 at the entrance. Attach a plan extract and revision.
Requirement
Building remains in use. Confirm access and timings.
Follow-up
Tender team asks. The planner updates the handover once the answer is confirmed.
Decision point
Before bid submission. Check impact on programme, measures and cost.
Example draft question
Phasing plan · phase 2 work zone
Tender documents · access to the building
Compare the phasing plan with the access requirement. With both references at hand, your team can check the draft question before submitting it.
Explore Tender ClarificationsWhich documents should you compare?
Start with the current phasing plan and the access requirements in the tender. Record the location, phase and revision from each document.
How do you keep an open issue visible in the programme?
Link it to the work zone and decision point, assign an owner and update the programme and handover when the answer is confirmed.
Who decides whether temporary access is feasible?
The responsible specialists assess the proposal against the site and its requirements. Baudex helps bring the relevant details and open questions together.
Bring your phasing plan and one access requirement. We’ll look at what your team needs to ask to reach an agreement.