An estimate your client can check.
You deliver the estimate in your client’s format. When a drawing changes, they need to know which items are affected. Baudex helps you prepare draft items from the project documents. You decide which quantities, price references and open issues go into the handover.
Worked estimate · Project Nova
What should go with the estimate?
The external wall subframes have been priced. The person receiving the estimate needs to trace the quantity and see what remains to be agreed.
Estimate item
External wall subframes
€30,600
excl. VAT
Quantity calculation
Reference: elevation drawing, page 4.
Does each home need six?
Find the current elevation drawing. Count any different house types separately before applying the same number to all homes.
Record the sheet and revision
The example item gives no revision. Confirm the current version and record it alongside the calculation.
Cost per subframe
Pricing basis from the worked estimate.
What does the installation cover?
The item lists labour separately. Record what those hours cover, such as positioning and fixing the subframe or making good at the external wall.
Record the rate source and scope
Include the pricing sheet or agreed rate. Flag any work that still needs confirmation and say who will resolve it.
Include with the estimate
Record the open issues against the same item code in the estimate.
What can the client take forward?
Hand over the item, its source and how the cost was built up together. Flag the two outstanding issues and agree who will update the item when either one changes.
Agree who signs off
The consultancy checks the count. The client and consultancy confirm the installation scope together. Update the item once those points are settled.
Keep open issues with the item.
First agree which item codes and units the client expects. For each item, keep the source, the price reference and any decision still needed. When a new revision arrives, you can see exactly which line needs another look.
How to review an AI-generated estimateHandover sheet · Subframes
Quantity
Elevation drawing p. 4 · 20 × 6 = 120 units.
Pricing
€145 materials + €110 labour per unit.
Open issues
Confirm the revision and installation scope.
Follow-up
The consultancy checks the count. The consultancy and client agree the installation scope.
From a draft item to your estimate.
Project Nova shows how Baudex prepares a draft line item with material and labour costs. Your team checks quantities and pricing and incorporates the client’s requirements before handover.
Explore Concept Estimating How an estimator checks an itemWhat should you agree up front?
How do you work with your client’s estimate format?
Walk through one sample item together. Agree the item code, unit, cost breakdown and exclusions, then carry those conventions through the estimate.
What do you do when a drawing is revised?
Find the items that reference the revised sheet. Compare it with the previous revision, recount the parts that changed and record the changes in the estimate.
Which documents do you need to produce a first draft?
Start with the current drawings, specification and pricing agreements that determine the item. Record anything still missing and who will provide it.
Bring one difficult item.
In the demo we’ll go through the quantity, pricing basis and decisions you need to hand that item over.