All articles

Estimating and measurement · Redactie Baudex

How to review an AI-generated estimate

Correct arithmetic alone does not make an estimate item ready to use. Use these five checks to see whether the quantity, source and pricing basis fit your scope of work.

Example from the article

Screed for 24 apartments

Calculated quantity

1,440 m²

The basis for 60 m² per apartment still needs checking.

In this article

Compare the line item with the scope

Does the item cover all four storeys or phase 1 only? In the example, that means 24 or 18 apartments. Also check whether supply, installation and substrate preparation belong to the same scope.

Record the selected phase, building elements, work and exclusions. Compare related items: is any work missing or counted twice?

Read the source in context

Which passage defines the screed specification? Open the cited document and read the surrounding text. Check whether a later revision or tender answer changed the specification.

Keep the document name, revision and location with your review. A reference makes information traceable; you check whether it applies to this item and phase.

Reconstruct the quantity

Does 60 m² come from the drawing, or is it an assumed area? The question remains open even if both calculations are correct.

One assumption, two scopes

All four storeys
24 × 60 m² = 1,440 m²
Phase 1 only
18 × 60 m² = 1,080 m²

Record the formula, unit and source of the dimension. Check apartment types, repetitions, openings and deductions. An unconfirmed dimension remains an assumption, even when the total has already been calculated.

Examine what the price includes

Does a price-book entry for 70 mm anhydrite fit the specified screed? Compare the unit, materials, labour and included work. The example rate of €28/m² does not itself establish a suitable project price.

Record the selected pricing basis and any adjustments. Consider access, phasing, small quantities and substrate work. A colleague can then see why you used or changed a standard rate.

See the worked screed item

Pass on the uncertainty

Can the next colleague explain the item without relying on your memory? They need the selected scope, source, quantity calculation and pricing basis.

Distinguish reviewed information from open assumptions. For each unresolved issue, record what is missing, who investigates and when the answer is needed.

What to hand over to your colleague

  • The agreed scope and any exclusions from the line item.
  • The source, with the document name, version and reference.
  • The calculation, unit, source of the measurement and pricing basis.
  • Open assumptions, including who will check them and when an answer is needed.

Example item · Screed

Provisional amount in this example

For all four storeys, the screed item comes to €40,320, based on 1,440 m² at an example rate of €28/m².

If only phase 1 applies, six apartments are outside the scope of this item. At the same rate, 1,080 m² comes to €30,240. That is €10,080 less.

Before finalising the estimate

  • The tender manager confirms which phase the bid covers.
  • The construction planner checks the 60 m² per apartment and records the drawing, revision and sheet.
  • The estimator records whether the rate includes supply, installation and preparation of the substrate.

Share these examples with your team.

Read the practical guide

Choose language

Dutch is selected.